Institute of Chemical Physics after A.B. Nalbandyan Division of Chemistry and Earth Sciences |
N | Investment project title | Development of production technology of the rust converter "LA-2" | |
1. | Sector | Protection against corrosion of pipelines for water and natural gas supply, industrial constructions, transport vehicles, bridges made of ferrous metals |
|
2. | Project description | It is planned to upgrade the pilot production installation, to purchase the necessary raw materials, technological and laboratory equipment aimed at increasing the producing capacity (up to 300-500 ton/year), as well as involvement and training of experts. Besides, advertising activity will be widened. |
|
3. | Project implementation period | 18 months | |
4. | Project location | A. Nalbandyan Institute of Chemical Physics of NAS RA | |
5. | Project overall cost (USD) | 60.000 | |
6. | Required investments (USD) | 60.000 | |
7. | Own funds (USD) | Pilot production area with equipment and setups, the developed technology of rust converter (substantiated by appropriate documentation and specification) | |
8. | Creation of jobs | At the beginning of the project | At the end of the project |
6 | 15 | ||
9. | Payback period | 23-24 months | |
10. | Annual profitability index | Correct annual profitability may be calculated after the project implementation. According to preliminary calculations profitabi | |
11. | Detailed costs | - |
|
12. | Offer to investor | It is offered to conduct negotiations concerning cooperation in the case of implementation. |
|
13. | Contact details | Levon Tavadyan, Director of A.Nalbandyan Institute of Chemical Physics of NAS RA |
Pilot production area of the rust converter "LA-2" |
Finished product of the rust converter |